Wessex Internet works in the Wylye Road Hanging Langford were delayed due to emergency Wessex Water works. They had to stop on 6 Mar, restarted on 10 Mar – but suspended again from the 11 Mar. They recommenced work on 20th – to complete by Monday 24th.
Once the work in the road is completed, they will need to complete the cabling, splicing and testing – prior to the installations to approximately 30 properties being made ‘live’. This had been forecast to be complete by the end of Mar. However, given the unforeseen delays this may now run into early April.